Date | Milestone |
---|---|
Jun 2007 | Preliminary Project Approval and Part 1 Expenditure Authority for Non-Combat System Integration Components received |
Mar 2008 | Award of Multi-Ship Contracts (Docking Work Periods and Refits) |
Oct 2008 | Effective Project Approval and Part 2 Expenditure Authority for the Combat System Integration Components |
Nov 2008 | Award of Combat System Integration Contract |
Fall 2010 | Commence 1st refit (HALIFAX) |
Spring 2011 | Commence 2nd refit (CALGARY) |
Fall 2011 | Commence 3rd refit (FREDERICTON) |
Spring 2012 | Commence 4th refit (WINNIPEG) |
Summer 2012 | Commence 5th refit (MONTREAL) |
Spring 2013 | Commence 6th refit (CHARLOTTETOWN) |
Spring 2013 | Commence 7th refit (VANCOUVER) |
Winter 2014 | Commence 8th refit (ST JOHN’S) |
Spring 2014 | Commence 9th refit (OTTAWA) |
Fall 2014 | Commence 10th refit (VILLE DE QUEBEC) |
Spring 2015 | Commence 11th refit (REGINA) |
Summer 2015 | Commence 12th refit (TORONTO) |
Winter 2019 | Project Close-Out |
Note: Refits - all refits 18 months duration.