11 February 2011 Print Write e-mail

Debris Accumulation

Clean-up operations:

  • We have revised the completion date for Scrivener Dam & Yarramundi Reach to Friday 18 February 2011 as a lot of small material is still required to be collected. The bulk of the large debris has now been removed;
  • Central Basin completed on Friday 24 December 2010;
  • Tarcoola Reach completed Wednesday 12 January 2011;
  • West Lake completed Wednesday 19 January 2011;
  • West Basin completed Friday 21 January 2011;
  • All islands completed Friday 21 January 2011; and
  • East Basin completed Monday 31 January 2011.

Next Phase of Works

The Request For Quotation (RFQ) for a suitably qualified contractor to remove stockpiles from beach areas and undertake remediation services closed Thursday 10 February 2011. A 2-3 week window is anticipated for the removal of the 5 stockpile sites around Lake Burley Griffin.

Last Updated on Friday, 11 February 2011 12:40